Tariff for Electric Consumption Charges
for
Sushant Golf City, Lucknow
Effective from 01/01/2012
Permanent Residential Connection (for Houses)
|
1
|
Unit Charges per KWH |
Rs 3.80 |
|
2
|
Fixed Charges per KWH per Month |
Rs 65.00 |
|
3 |
System Loading Charges per KWH (One time payment at the time of release of Load) |
Rs 300.00
|
Temporary Connection for Construction of Houses
|
1
|
Unit Charges per KWH |
Rs 5.75 |
|
3 |
System Loading Charges per KWH (upto 50 KWH) (One time payment at the time of release of Load) |
Rs 300.00
|
|
4 |
System Loading Charges per KWH (above 50 KWH) (One time payment at the time of release of Load)
|
Rs 1000.00
|
- Above rates are subject to change / revision at any time without any prior intimation or information.
- Please submit separate application for electric connection on prescribed format E-1.
- The electric connection shall be made within 7 days from the date of payment of System Loading Charges.
- Prepaid Electric Recharge Coupons are available at our office on cash payment basis and timings for issue of Prepaid Electric Recharges Coupons :-
Mon – Fri 10:00 am to 1.00 pm and 2.00 pm to 5:00 pm
Saturdays 10.00 am to 1.00 pm only
Sunday & Holiday Closed
- For any query regarding Electric Connection / Complaints / Recharge, please contact during office hours :
Mr. Indresh N Tripathi (Manager – Services)
Cell : 8874207731 or Land Line No : 0522-6591125, 8874207777